The works for a 1,000–3,000 sq ft office usually take one to two weeks, but approvals and building rules can add as much time again. Here’s a realistic timeline.
Updated 26 October 2026
In short: Works for a 1,000–3,000 sq ft office usually take 5–10 working days, but permits, move-out and the joint inspection add one to three weeks. Start planning 4–8 weeks before your handover date.
| Office size | Works on site |
|---|---|
| Under 1,000 sq ft | 3–5 working days |
| 1,000–3,000 sq ft | 5–10 working days |
| 3,000–10,000 sq ft | 2–4 weeks |
These assume normal access. Heavy fit-outs with server rooms, raised floors or extensive M&E take longer.
Altogether, start 4–8 weeks before the handover date.
Our office move-out checklist covers the rest of the move.
| Week before handover | What happens |
|---|---|
| 8–6 | Site survey, quotation, landlord confirms the scope |
| 5–4 | Building works permit submitted and approved |
| 3 | Move-out of staff, IT and furniture |
| 2–1 | Reinstatement works, about 7–10 working days |
| Handover week | Joint inspection, remarks fixed, handover signed |
Partitions and flooring usually take the most time on site. See partition wall removal, carpet removal and vinyl flooring removal for each step.
We handle office reinstatement across Singapore, with a free site survey and an itemised quotation. See office reinstatement, or WhatsApp us photos of the unit.
Send photos, the floor plan and your handover date. Site surveys are free and every quotation is itemised.
Can’t see yours? Send it on WhatsApp with a photo of the unit.
Works for a 1,000–3,000 sq ft office usually take 5–10 working days, plus time for permits, move-out and the joint inspection.
Four to eight weeks before your handover date.
Often yes. Many CBD buildings only allow noisy works after hours or at weekends.
The landlord may carry out the remaining works and deduct the cost from your deposit, or charge for the extra days, depending on the lease.
We’ll reply with an initial estimate and a time for a free site survey.